What’s happening at Chobham Manor

Things are moving quickly at Chobham Manor…

May 2013 – a Zonal Masterplan was submitted to the Park’s planning authority. It shows how Chobham Manor will meet the planning guidelines

June/July 2013 – the project team prepared a planning application including more details about how the first new homes will look at Chobham Manor, to be submitted to the Park’s planning authority

January 2014 – the Park’s planning authority approved Phase 1 of Chobham Manor

March 2014 – Honor Lea Avenue and Olympic Park Avenue, which run through Chobham Manor, are opened

May 2014 – Sales and Marketing Suite opened on site as the first homes in Phase 1 went on sale

June 2014 – work started on the first homes at Chobham Manor

Autumn 2014 – anticipated submission of planning application for the second phase of homes at Chobham Manor

2015 – first homes ready to move into